Precast Concrete
- Controlled environment- alleviating all environmental factors sun, wind, rain.
- Control mix designs in house- high quality durable concrete (low W/Co ratios).
- Quality Assurance systems, post and pre pour checks.
+ click to enlarge
- Drawing
- Mould table to be clean and free of imperfections prior to set up
- Form work
- Set up dimensionally correct
- Reinforcement and cast in items respecting drawings
- Concrete preparation
- Placement of concrete
- Stripping
- Handling & storage
- Final inspection
- AS3610 for off-form concrete
- Class 2
- Always view samples or similar projects to create the right expectation
- Understand you are dealing with natural products
- Accurate scheduling, providing documentation is complete and sufficient lead times allowed for workshop detailing 9-12 weeks lead time currently
- Not effected by weather
+ click to enlarge
- Greater synergies could be realized in the manufacture of precast if repeat panels on elevations were able to be cast from bottom to top in a single mould. Current practice is level by level around the building.
- For this to happen give the manufacture greater lead times.
- Repetitive and standard features.
- Ensure documentation is complete, including workshop drawings; this allows for better planning at manufactures facilities.
- Be prepared to pay manufacture for off site payments for panels manufactured.
- Standard panel thickness
- Standard cast plates and fixings
+ click to enlarge
- Requires high degree of quality control.
- On site manufacture allows control and conditioning of raw materials, avoids contamination of materials; often experienced with premixed suppliers.
- Gives you control of water demand in concrete, maintaining integrity of water cement ratios. Inconsistent water demands and the practice of adding water will change colour and texture of concrete.
- Maximise panel area, panels @20m² or better, target 10 tonne for flat lift out of beds; also dependant on crane size and area on site.
- Minimise number of panels, effectively reducing labour, truck movements and cranage.
- Greater consideration required by all on lifting procedures to match site environment and practices of riggers.
- Design for lifting precast.
- Design to use proprietary lifting systems.
- Include erection teams in at early stages of project.
- Employ correct lifting procedures.
- Use proprietary lifting system.
- Internal audits on safety procedures and JSA’a.
- Maintain housekeeping.
- Regular scheduled maintenance of cranes and equipment.
- Erection sequence determines loads.
- Site access for trucks.
- Planning will reduce transport costs.
- Maximum height of panels in A frames 4.3 metres.
- Length to suit trailer configurations generally 12 metres, consider site application for riggers.